📚 Interview question

What is an error budget policy, and how would you get product leadership to agree to one before the next incident?

Covers what an error budget policy is, what it typically says (thresholds and consequences), and how to get product leadership to agree to it before an incident.

Senior Behavioral Advanced error-budget production reliability slo stakeholder-management

🎯 Key points

  • Error budget = 1 minus the SLO over a window (99.9% over 28 days is about 40 minutes of total failure)
  • Set SLOs with product, from what customers notice (journeys, support contacts, feedback), not from what's easy to measure
  • Policy sets thresholds: e.g. 50% burned, review risky releases; 100% burned, freeze non-urgent releases and prioritise reliability until it recovers
  • Exceptions (security fixes, legal deadlines) decided by a named person
  • Agree it before an incident, when nobody is under pressure; pitch it as freedom to ship while budget remains
  • Pilot on one service with a leadership sponsor
  • Review quarterly: adjust SLOs and thresholds to real performance and changing business needs

⏱ 30-second answer

An error budget is the unreliability your SLO allows: at 99.9% over 28 days that's about 40 minutes of total failure. An error budget policy is a short, agreed document that says what happens as the budget is spent: for example, at 50% burned the team reviews risky releases; at 100% it freezes non-urgent releases and works on reliability until the budget recovers, with exceptions such as security fixes decided by a named person.

To get product leadership to agree, I set the SLOs with them, from the customer journeys and support data they care about, and propose the policy when things are calm, framed as freedom: while budget remains, the team ships as fast as it likes. I pilot on one service, get a leadership sponsor, and review it quarterly so SLOs and thresholds keep matching real performance and business needs. The trade-off is that a freeze can delay a launch, which is exactly why the thresholds must be agreed up front.

🔍 What the interviewer is checking

Checks understanding of SLO-based prioritisation and influencing leadership.